Transbay Terminal’s two-station solution

Pub date April 10, 2009
SectionPolitics Blog

By Steven T. Jones

As the deadline approaches for the Transbay Joint Powers Authority to figure out how its massive new Transbay Terminal will accommodate the California High-Speed Rail project, it appears the agency may pursue a two-station solution to the capacity question.

TJPA spokesperson Adam Alberti tells the Guardian that involved agencies are hoping operational adjustments can be made to handle up to eight trains per hour at Transbay, and that the additional four trains per hour that the California High-Speed Rail Authority says it wants might have to stop at the existing 4th and Townsend station.

He said there is a growing consensus against building a second floor of train platforms, which could add $1 billion to the price of the project. The TJPA board needs to land on a plan by May so current contracts can be issued and so regional agencies can come together on a request for about $1 billion in federal stimulus money when the state makes its formal request for federal high-speed rail funding in June.

CHSRA Chair Quentin Kopp continues to question the Transbay Terminal project, saying its schedule and location have been dictated by its bus component and noting that its costs have been creeping ever higher. “This has all the earmarks of San Francisco’s Big Dig.”